Three teams in the Agile Release Train are working on the same Feature. Team A is a component team, and Teams B and C are feature teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A’s piece in the first week of the IP Iteration. Why is this an anti-pattern?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 03:30
Joe said “your speech was really great, i loved it.” his criticism lacks which component of effective feedback? a) he did not recognize his ethical obligations b) he did not focus on behavior c) he did not stress the positive d) he did not offer any specifics
Answers: 2
question
Business, 22.06.2019 16:40
Job 456 was recently completed. the following data have been recorded on its job cost sheet: direct materials $ 2,418 direct labor-hours 74 labor-hours direct labor wage rate $ 13 per labor-hour machine-hours 137 machine-hours the corporation applies manufacturing overhead on the basis of machine-hours. the predetermined overhead rate is $14 per machine-hour. the total cost that would be recorded on the job cost sheet for job 456 would be: multiple choice $3,380 $5,298 $6,138 $2,622
Answers: 1
question
Business, 22.06.2019 22:10
Scoresby co. uses 6 machine hours and 2 direct labor hours to produce product x. it uses 8 machine hours and 16 direct labor hours to produce product y. scoresby's assembly and finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. how much overhead cost will be charged to the two products? a. product x = $1,440; product y = $2,560 b. product x = $1,760; product y = $4,480 c. product x = $3,200; product y = $9,600 d. product x = $800; product y = $800
Answers: 1
question
Business, 23.06.2019 01:00
"consists of larger societal forces that affect how a company engages and serves its customers."
Answers: 1
You know the right answer?
Three teams in the Agile Release Train are working on the same Feature. Team A is a component team,...
Questions
question
Mathematics, 22.03.2021 18:50
question
Mathematics, 22.03.2021 18:50
question
English, 22.03.2021 18:50
question
History, 22.03.2021 18:50
Questions on the website: 13722367