Business, 31.07.2020 16:01 TJxx187

The following data relate to factory overhead cost for the production of 10,000 computers: Actual: Variable factory overhead $262,000
Fixed factory overhead 90,000
Standard: 14,000 hrs. at $25 350,000
If productive capacity of 100% was 15,000 hours and the total factory overhead cost budgeted at the level of 14,000 standard hours was $356,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $6.00 per hour.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:50
Explain whether each of the following events increases or decreases the money supply. a. the fed buys bonds in open-market operations. b. the fed reduces the reserve requirement. c. the fed increases the interest rate it pays on reserves. d. citibank repays a loan it had previously taken from the fed. e. after a rash of pickpocketing, people decide to hold less currency. f. fearful of bank runs, bankers decide to hold more excess reserves. g. the fomc increases its target for the federal funds rate.
Answers: 3
question
Business, 23.06.2019 00:20
Barney corporation recognized a $100 million preferred stock balance on 12/31/2019. on january 1, 2020, barney issued $10 million in preferred dividends. on the same date, barney raised an additional $20 million via a new issuance of preferred stock. on december 31, 2020, the market value of the original amount of preferred shares rose $5 million. under us gaap, the 12/31/2020 year ending preferred stock balance is:
Answers: 3
question
Business, 23.06.2019 01:30
How is systematic decision making related to being financially responsible
Answers: 1
question
Business, 23.06.2019 02:00
Suppose that a major city’s main thoroughfare, which is also an interstate highway, will be completely closed to traffic for two years, from january 2014 to december 2015, for reconstruction at a cost of $535 million. if the construction company were to keep the highway open for traffic during construction, the highway reconstruction project would take much longer and be more expensive. suppose that construction would take four years if the highway were kept open, at a total cost of $800 million. the state department of transportation had to make its decision in 2014, one year before the start of construction (so that the first payment was one year away). so the department of transportation had the following choices: (i) close the highway during construction, at an annual cost of $267.5 million per year for two years. (ii) keep the highway open during construction, at an annual cost of $200 million per year for four years. now suppose the interest rate is 80%. calculate the present value of the costs incurred under each plan.
Answers: 3
You know the right answer?
The following data relate to factory overhead cost for the production of 10,000 computers: Actual:...
Questions
question
Mathematics, 06.04.2021 22:30
question
Mathematics, 06.04.2021 22:30
question
Social Studies, 06.04.2021 22:30
question
Geography, 06.04.2021 22:30
question
Mathematics, 06.04.2021 22:30
question
Mathematics, 06.04.2021 22:30
Questions on the website: 13722362