subject
Business, 09.07.2020 01:01 khush77

Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Activity Description Immediater Normal Crash Normal Cost Crash Cost
Predecessor Time (weeks) Time (weeks) ($1000s) ($1000s)
A Plan needs 10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60
a. Develop a project network.
b. Develop an activity schedule.
c. What are the critical activities, and what is the expected project completion time?
d. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
e. Develop an activity schedule for the crashed project.
f. What added project cost is required to meet the six-month completion time?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:30
Needs to schedule the staffing of the center. it is open from 8am until midnight. larry has monitored the usage of the center at various times of the day and determined that the following number of computer consultants are required: time of dayminimum number of consultants required to be on duty8 am-noon4noon-4 pm84pm-8pm108pm-midnight6 two types of computer consultants can be hired: full-time and part-time. the full- time consultants work for eight consecutive hours in any of the shifts: morning (8am- 4pm), afternoon (noon-8pm) and evening (4pm-midnight). full-time consultants are paid $14 per hour. part-time consultants can be hired to work any of the four shifts listed in the table. part-time consultants are paid $12 per hour. an additional requirement is that during every time period, there must be at least two full-time consultants on duty for every part-time consultant on duty. larry would like to determine how many full-time and part-time consultants should work each shift to meet the above requirements at the minimum possible cost. formulate this as an lp problem. you must define your variables clearly
Answers: 2
question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 09:00
According to this excerpt, a key part of our national security strategy is
Answers: 2
question
Business, 22.06.2019 14:40
Which of the following would classify as a general education requirement
Answers: 1
You know the right answer?
Office Automation, Inc., developed a proposal for introducing a new computerized office system that...
Questions
question
Biology, 31.08.2019 20:20
question
English, 31.08.2019 20:20
question
Geography, 31.08.2019 20:20
question
Mathematics, 31.08.2019 20:20
Questions on the website: 13722363