On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 11:30
When the amount for land is 36,000 and the amount paid for expenses is 10,000, the balance of total asset is
Answers: 2
question
Business, 22.06.2019 19:10
Do it! review 16-3 the assembly department for right pens has the following production data for the current month. beginning work in process units transferred out ending work in process 0 22,500 16,000 materials are entered at the beginning of the process. the ending work in process units are 70% complete as to conversion costs. compute the equivalent units of production for (a) materials and (b) conversion costs. materials conversion costs the equivalent units of production
Answers: 2
question
Business, 22.06.2019 21:20
Rediger inc., a manufacturing corporation, has provided the following data for the month of june. the balance in the work in process inventory account was $28,000 at the beginning of the month and $20,000 at the end of the month. during the month, the corporation incurred direct materials cost of $56,200 and direct labor cost of $29,800. the actual manufacturing overhead cost incurred was $53,600. the manufacturing overhead cost applied to work in process was $52,200. the cost of goods manufactured for june was:
Answers: 2
question
Business, 22.06.2019 22:50
Amonopolist’s inverse demand function is p = 150 – 3q. the company produces output at two facilities; the marginal cost of producing at facility 1 is mc1(q1) = 6q1, and the marginal cost of producing at facility 2 is mc2(q2) = 2q2.a. provide the equation for the monopolist’s marginal revenue function. (hint: recall that q1 + q2 = q.)mr(q) = 150 - 6 q1 - 3 q2b. determine the profit-maximizing level of output for each facility.output for facility 1: output for facility 2: c. determine the profit-maximizing price.$
Answers: 3
You know the right answer?
On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560....
Questions
question
Mathematics, 19.02.2021 04:20
question
Mathematics, 19.02.2021 04:20
question
Geography, 19.02.2021 04:20
question
Mathematics, 19.02.2021 04:20
question
Geography, 19.02.2021 04:20
question
Mathematics, 19.02.2021 04:20
question
Business, 19.02.2021 04:20
question
Mathematics, 19.02.2021 04:20
Questions on the website: 13722367