Lake Erie Company uses a plantwide overhead rate with machine hours as the allocation base. Next year, 770,000 units are expected to be produced taking 0.85 machine hours each. How much overhead will be assigned to each unit produced given the following estimated amounts? Estimated: Department 1 Department 2
Manufacturing overhead costs $3,141,500 $1,571,000
Direct labor hours 167,000 DLH 267,000 DLH
Machine hours 267,000 MH 192,000 MH
a) $10.86 per unit
b) $8.73 per unit
c) $4.22 per unit
d) $11.77 per unit
e) $10 per unit

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 06:40
At april 1, 2019, the food and drug administration is in the process of investigating allegations of false marketing claims by hulkly muscle supplements. the fda has not yet proposed a penalty assessment. hulkly’s fiscal year ends on december 31, 2018. the company’s financial statements are issued in april 2019. required: for each of the following scenarios, determine the appropriate way to report the situation. 1. management feels an assessment is reasonably possible, and if an assessment is made an unfavorable settlement of $13 million is reasonably possible. 2. management feels an assessment is reasonably possible, and if an assessment is made an unfavorable settlement of $13 million is probable. 3. management feels an assessment is probable, and if an assessment is made an unfavorable settlement of $13 million is reasonably possible. 4. management feels an assessment is probable, and if an assessment is made an unfavorable settlement of $13 million is probable.
Answers: 1
question
Business, 22.06.2019 13:50
Classify each of the following items as a public good, a private good, a natural monopoly good, or a common resource.(a) measles vaccinations (b) tuna in the pacific ocean (c) airline service in the united states (d) local storm-water system
Answers: 1
question
Business, 22.06.2019 14:50
Ann chovies, owner of the perfect pasta pizza parlor, uses 20 pounds of pepperoni each day in preparing pizzas. order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. if she were to order 80 pounds of pepperoni at a time, what would be the average inventory level?
Answers: 3
question
Business, 22.06.2019 17:30
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
You know the right answer?
Lake Erie Company uses a plantwide overhead rate with machine hours as the allocation base. Next yea...
Questions
Questions on the website: 13722367