Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20
2 - 3 2 60 60
3 1 4 0 70 0
4 1 2 1 50 10
5 2 5 3 100 60
6 3 2 1 90 100
7 4 5 1 50 30
8 5 2 0 60 40
9 6,7,8 3 1 200 200
Consider the project above. If the indirect costs of the project are: $90 at 15 days, $75 at 14 days, $50 at 13 days, $40 at 12 days, and $30 at 11 days.
Please help crash this project in a manner that minimizes the sum of the total direct and indirect costs.
What is the current estimated project duration in days without any crashing?
A. 11
B. 14
C. 13
D. 15

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 06:00
Why might a business based on a fad be a good idea? question 2 options: fads bring in the most customers. some fads are longer lasting than expected. fads have made some business owners incredibly wealthy. fads can take a business in a new direction.
Answers: 2
question
Business, 22.06.2019 11:00
Using a cps-sample of 7,440 individuals, you estimate the following regression: = 20.91 - 2.61 x female where female is a binary variable that takes on the value of 1 for females and is 0 otherwise. the standard error on the coefficient on female is 0.25. the 95% confidence interval for the gender wage gap, or the amount that females earn less, is: a) [-3.10, -2.12] b) [18.30, 23.52] c) [-3.02, -2.20] d) [-1.96, -1.64]
Answers: 3
question
Business, 22.06.2019 23:30
Mystic bottling company bottles popular beverages in the bottling department. the beverages are produced by blending concentrate with water and sugar. the concentrate is purchased from a concentrate producer. the concentrate producer sets higher prices for the more popular concentrate flavors. a simplified bottling department cost of production report separating the cost of bottling the four flavors follows:
Answers: 3
question
Business, 23.06.2019 09:00
Jonathan’s class has 30 boys. of the students in his class, 60% are girls. how many girls are in jonathan’s class? (a)75 (b)60 (c)45 (d)20
Answers: 1
You know the right answer?
Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20
Questions
Questions on the website: 13722361