The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z a) Construct a product structure. Identify all levels, parents, and components. b) Prepare a time-phased product structure..
Answers: 2
Business, 22.06.2019 07:00
Imagine you own an established startup with growing profits. you are looking for funding to greatly expand company operations. what method of financing would be best for you?
Answers: 2
Business, 22.06.2019 15:00
(a) what do you think will happen if the price of non-gm crops continues to rise? why? (b) what will happen if the price of non-gm food drops? why?
Answers: 2
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units...
English, 24.07.2019 21:30
English, 24.07.2019 21:30