Romeo Construction enters into a contract with a customer to build a warehouse for $800,000 on March 30, 2014, with an additional performance bonus of $50,000 if the building is completed by July 31, 2014. The bonus is reduced by $10,000 each week that completion is delayed.
Romeo commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:

Completed by Probability
July 31, 2014 65%
August 7, 2014 25%
August 14, 2014 5%
August 21, 2014 5%

The transaction price for this transaction is .

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
The federal act which provided over $7 billion to the epa to protect and promote "green" jobs and a healthier environment is the - national environmental policy act. - resource recovery act.- resource conservation and recovery act.- american recovery and reinvestment act. - clean air act.
Answers: 1
question
Business, 22.06.2019 09:40
The wall street journal reported that walmart stores inc. is planning to lay off 2,300 employees at its sam's club warehouse unit. approximately half of the layoffs will be hourly employees (the wall street journal, january 25-26, 2014). suppose the following data represent the percentage of hourly employees laid off for 15 sam's club stores. 55 56 44 43 44 56 60 62 57 45 36 38 50 69 65 (a) compute the mean and median percentage of hourly employees being laid off at these stores. (b) compute the first and third quartiles. (c) compute the range and interquartile range. (d) compute the variance and standard deviation. (e) do the data contain any outliers? (f) based on the sample data, does it appear that walmart is meeting its goal for reducing the number of hourly employees?
Answers: 1
question
Business, 22.06.2019 21:30
Consider the following three bond quotes; a treasury note quoted at 87.25, and a corporate bond quoted at 102.42, and a municipal bond quoted at 101.45. if the treasury and corporate bonds have a par value of $1,000 and the municipal bond has a par value of $5,000, what is the price of these three bonds in dollars? multiple choice $872.50, $1,000, $1,000, respectively $1,000, $1,024.20, $1,001.45, respectively $872.50, $1,024.20, $5,072.50, respectively $1,000, $1,000, $1,000, respectively
Answers: 3
question
Business, 22.06.2019 21:40
Inventory by three methods; cost of goods sold the units of an item available for sale during the year were as follows: jan. 1 inventory 20 units at $1,800 may 15 purchase 31 units at $1,950 aug. 7 purchase 13 units at $2,040 nov. 20 purchase 16 units at $2,100 there are 18 units of the item in the physical inventory at december 31. determine the cost of ending inventory and the cost of goods sold by three methods, presenting your answers in the following form: round your final answers to the nearest dollar. cost inventory method ending inventory cost of goods sold a. first-in, first-out method $ $ b. last-in, first-out method $ $ c. weighted average cost method $ $
Answers: 3
You know the right answer?
Romeo Construction enters into a contract with a customer to build a warehouse for $800,000 on March...
Questions
question
Physics, 18.10.2019 19:30
Questions on the website: 13722363