Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2017, are presented below:
Bid Price: $450,000
Contract cost: 2016 -180,000
2017 -195,000
Gross Profit: 75,000
Estimated Cost to Complete:
12/31/2016 $200,000
12/31/2017 0
1. Assuming BCC uses the percentage-of-completion method of revenue recognition, the gross profit recognized in 2016 would be (rounded to the nearest thousand):
2. Assuming BCC uses the percentage-of-completion method of recognition the gross profit recognized in 2017 would be (rounded to the nearest thousand):
3. Assuming BCC used the completed contract method to recognize revenue, what would gross profit have been in 2016 and 2017 (rounded to the nearest thousand)?
2016 2017
a. $36,000 $39,000
b. $30,000 $45,000
c. $70,000 $5,000
d. $ 0 $75,000
4. Assuming BCC used the cost recovery method to recognize revenue under IFRS, what would gross profit have been in 2016 and 2017 (rounded to the nearest thousand)?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:00
What should a food worker use to retrieve ice from an ice machine?
Answers: 1
question
Business, 22.06.2019 22:20
With q7 assume the sweet company uses a plantwide predetermined overhead rate with machine-hours as the allocation base.and for q 10,11,13,and 14,assume that the company use department predetermined overhead rates with machine-hours as the allocation bade in both departements.7. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answers to nearest whole dollar.)total price for the job for job p -job q selling price per unit for job p q . how much manufacturing overhead was applied from the molding department to job p and how much was applied to job q? (do not round intermediate calculations.) job p job q manufacturing overhead applied for job p for job q . how much manufacturing overhead was applied from the fabrication department to job p and how much was applied to job q? (do not round intermediate calculations.)job p job q manufacturing overhead applied for job p for job q . if job q included 30 units, what was its unit product cost? (do not round intermediate calculations. round your final answer to nearest whole dollar.)14. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answer to nearest whole dollar.)total price for the job p for job q selling price per unit for job p for job q
Answers: 1
question
Business, 22.06.2019 22:50
Which of these makes a student loan different from other types of loans
Answers: 1
question
Business, 23.06.2019 02:00
Which type of unemployment would increase if workers lost their jobs because their positions were replaced by an automated process? a) cyclical b) frictional c) international d) structural
Answers: 1
You know the right answer?
Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2017, are presen...
Questions
question
Mathematics, 30.09.2019 06:30
Questions on the website: 13722363