A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 02:00
Corporations with suppliers, vendors, and customers all over the globe are referred to as : a) global corporations b) international corporations c) multinational corporations d) multicultural corporations
Answers: 2
question
Business, 22.06.2019 23:10
Until recently, hamburgers at the city sports arena cost $4.70 each. the food concessionaire sold an average of 13 comma 000 hamburgers on game night. when the price was raised to $5.40, hamburger sales dropped off to an average of 6 comma 000 per night. (a) assuming a linear demand curve, find the price of a hamburger that will maximize the nightly hamburger revenue. (b) if the concessionaire had fixed costs of $1 comma 500 per night and the variable cost is $0.60 per hamburger, find the price of a hamburger that will maximize the nightly hamburger profit.
Answers: 1
question
Business, 23.06.2019 02:50
Three years ago, stock tek purchased some five-year macrs property for $82,600. today, it is selling this property for $31,500. how much tax will the company owe on this sale if the tax rate is 34 percent? the macrs allowance percentages are as follows, commencing with year 1: 20.00, 32.00, 19.20, 11.52, 11.52, and 5.76 percent.
Answers: 1
question
Business, 23.06.2019 14:00
Max has set some financial goals and created a budget. what else does max need to have a complete financial plan? a. loan information, insurance plan, and a saving and investing plan b. net worth statement, risk management plan, and investment principals c. net worth statement, insurance plan, and a saving and investing plan d. net worth statement, spreadsheet, and risk management plan
Answers: 1
You know the right answer?
A project to develop technology training seminars is 5 days behind schedule at day 65. It had a plan...
Questions
question
Mathematics, 02.11.2019 06:31
Questions on the website: 13722367