In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 14:30
Taking commercial paper means the holder acts honestly
Answers: 1
question
Business, 22.06.2019 17:30
The purchasing agent for a company that assembles and sells air-conditioning equipment in a latin american country noted that the cost of compressors has increased significantly each time they have been reordered. the company uses an eoq model to determine order size. what are the implications of this price escalation with respect to order size? what factors other than price must be taken into consideration?
Answers: 1
question
Business, 22.06.2019 20:30
This problem has been solved! see the answercompute and interpret altman's z-scoresfollowing is selected financial information for ebay, for its fiscal years 2005 and 2006.(in millions, except per share data) 2006 2005current assets $ 4,970.59 $ 3,183.24current liabilities 2,518.39 1,484.93total assets 13,494.01 11,788.99total liabilities 2,589.38 1,741.00shares outstanding 1,368.51 1,404.18retained earnings 4,538.35 2,819.64stock price per share 30.07 43.22sales 5,969.74 4,552.40earnings before interest and taxes 1,439.77 1,445.18compute and interpret altman z-scores for the company for both years. (do not round until your final answer; then round your answers to two decimal places.)2006 z-score = answer2005 z-score = answerwhich of the following best describes the company's likelihood to go bankrupt given the z-score in 2006 compared to 2007.the z-score in 2006 is half of the 2005 score. both z-scores are well above the score that represents a healthy company.the z-score in 2006 is double the 2005 score. the z-score has increased sharply, which suggests the company has greatly increased the risk of bankruptcy.the z-score in 2006 is half of the 2005 score. the z-score has decreased sharply, which suggests the company is in financial distress.the z-score in 2006 is double the 2005 score. the z-score has increased sharply, which suggests the company has greatly lowered the risk of bankruptcy.
Answers: 3
question
Business, 22.06.2019 21:50
Search engines generate revenue through pay-per-click (each time a user clicks a link to a retailer’s website); pay-per-call (each time a user clicks a link that takes the user to an online agent waiting for a call); or pay-per-conversion (each time a website visitor is converted to a customer)
Answers: 3
You know the right answer?
In month 9 the following project information is available: actual cost is $2,000, earned value is $2...
Questions
question
Mathematics, 02.10.2019 19:00
question
Health, 02.10.2019 19:00
Questions on the website: 13722367