Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:00
Factors like the unemployment rate,the stock market,global trade,economic policy,and the economic situation of other countries have no influence on the financial status of individuals. true or false
Answers: 1
question
Business, 22.06.2019 11:10
How much are you willing to pay for a zero that matures in 10 years, has a face value of $1,000 and your required rate of return is 7%? round to the nearest cent. do not include a dollar sign in your answer. (i.e. if your answer is $432.51, then type 432.51 without $ sign)
Answers: 1
question
Business, 22.06.2019 22:00
The company is experiencing an increase in competition, and at the same time they are building more production facilities in southeast asia. in this scenario, the top management team is most likely to multiple choice increase the cost of their products. restructure to reflect a more bureaucratic, stable organization. pull decision-making responsibility from low-level management, taking it on themselves. give lower-level managers the authority to make decisions to benefit the firm. rid themselves of all buffering product.
Answers: 3
question
Business, 22.06.2019 22:00
Which of the following is a function performed by market prices? a. market prices communicate information to buyers and sellers. b. market prices coordinate the decisions of buyers and sellers. c. market prices motivate entrepreneurs to produce those products that are currently most desired relative to their costs of production. d. all of the above are functions performed by market prices.
Answers: 2
You know the right answer?
Subcontractor deliveries are difficult to schedule with the critical chain project methodology becau...
Questions
question
Mathematics, 18.12.2019 03:31
question
Mathematics, 18.12.2019 03:31
Questions on the website: 13722367