Exercise 22-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases.

Process time 7.0 days
Inspection time 0.6 days
Move time 4.8 days
Wait time 5.0 days

1. Compute the company's manufacturing cycle time
2. Compute the company's manufacturing cycle efficiency

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:00
Jorge is a manager at starbucks. his operational plan includes achieving annual sales of $4,000,000 for his store. with only one month left to end of the fiscal year, jorge realizes that he won't reach his annual sales goal. what are his options?
Answers: 2
question
Business, 21.06.2019 20:30
At a young age, ebony's coaches were confident she had the potential to be a world-class swimmer with a future coaching career. after four years on an athletic scholarship and olympic experience under her belt, she chose a different path. with her savings and personal connections, she rented a corner building in a bustling san francisco neighborhood and pursued her dream: a surf shop business. ebony's dream was rooted in which basic right of free-market capitalism?
Answers: 3
question
Business, 22.06.2019 10:50
Bill dukes has $100,000 invested in a 2-stock portfolio. $62,500 is invested in stock x and the remainder is invested in stock y. x's beta is 1.50 and y's beta is 0.70. what is the portfolio's beta? do not round your intermediate calculations. round the final answer to 2 decimal places.
Answers: 2
question
Business, 22.06.2019 16:40
Based on what you learned about time management which of these statements are true
Answers: 1
You know the right answer?
Exercise 22-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcase...
Questions
question
Mathematics, 26.01.2020 02:31
Questions on the website: 13722367