A process that produces part A operates for 480 minutes a day. The required daily output for part A is 320 units. If the same process must also produce 130 units per day of part B, what is the average required cycle time (CT) for both products if the goal is to achieve the minimum required daily production capacity of the process?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 14:30
Producers can create their maximum combination of goods, s long as what?
Answers: 3
question
Business, 22.06.2019 00:30
How did lani lazzari show her investors she was a good investment? (site 1)
Answers: 3
question
Business, 22.06.2019 09:20
Which statement best defines tuition? tuition is federal money awarded to a student. tuition is aid given to a student by an institution. tuition is money borrowed to pay for an education. tuition is the price of attending classes at a school.
Answers: 1
question
Business, 22.06.2019 11:50
Which of the following does not offer an opportunity for timely content? evergreen content news alerts content that suits seasonal consumption patterns content that matches a situational trigger content that addresses urgent pain points
Answers: 2
You know the right answer?
A process that produces part A operates for 480 minutes a day. The required daily output for part A...
Questions
question
Mathematics, 29.04.2021 20:10
question
English, 29.04.2021 20:10
question
English, 29.04.2021 20:10
question
Social Studies, 29.04.2021 20:10
question
Biology, 29.04.2021 20:10
Questions on the website: 13722367