Production estimates for August for Jay Company are as follows:

Estimated inventory (units), August 1 12,000
Desired inventory (units), August 31 9,000
Expected sales volume (units), August 75,000
For each unit produced, the direct materials requirements are as follows:

Material A ($5 per lb.) 3.0 lbs.
Material B ($18 per lb.) 0.5 lb.

The number of pounds of Materials A and B required for August production is

a.216,000 lbs. of A; 72,000 lbs. of B

b.225,000 lbs. of A; 37,500 lbs. of B

c.234,000 lbs. of A; 39,000 lbs. of B

d.216,000 lbs. of A; 36,000 lbs. of B

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:40
Anew equipment has been proposed by engineers to increase the productivity of a certain manual welding operation. the investment cost is $25,000, and the equipment will have a market value of $5,000 at the end of a study period of five years. increased productivity attributable to the equipment will amount to $10,000 per year after operating costs have been subtracted from the revenue generated by the additional production. if marr is 10%, is investing in this equipment feasible? use annual worth method.
Answers: 3
question
Business, 22.06.2019 13:30
If the economy were in the contracting phase of the business cycle, how might that affect your ability to find work?
Answers: 2
question
Business, 22.06.2019 20:40
Review the wbs and gantt chart you created previously. propose three to five additional activities that would you estimate resources and durations. now, identify at least eight milestones for the recreation and wellness intranet project. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone. add your activities and milestones to your gantt chart, creating a new gantt chart. estimate the task durations and enter dependencies as appropriate. remember that your schedule goal for the project is six months. copy the gantt chart and network diagram to a word document.
Answers: 2
question
Business, 23.06.2019 00:00
Both renewable and nonrenewable resources are used within our society. how do the uses of nonrenewable resources compare to the uses of renewable resources?
Answers: 1
You know the right answer?
Production estimates for August for Jay Company are as follows:

Estimated inventory (un...
Questions
question
Mathematics, 05.01.2021 22:40
question
Biology, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
English, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Mathematics, 05.01.2021 22:40
question
Chemistry, 05.01.2021 22:40
Questions on the website: 13722360