The standards for product V28 call for 8.6 pounds of raw material that costs $19.00 per pound. Last month, 2,600 pounds of the raw material was purchased for $48,880. The actual output of the month was 270 units of product V28. A total of 2,500 pounds of the raw material were used to produce this output. The direct materials purchase variance is computed when the materials are purchased.

a. What is the material price variance for the month?

b. What is the materials quantity variance for the month?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 17:50
When borrowers want funding to pay for different projects, they go to the loanable funds market and acquire funds through either indirect finance or direct finance. below, you are given five different scenarios. is each an example of direct finance or indirect finance?
Answers: 2
question
Business, 22.06.2019 06:40
As a finance manager at allsports communication, charlie worries about the firm's borrowing requirements for the upcoming year. he knows the benefit of estimating allsports' cash disbursements and short-term investment expectations. facing these concerns, a(n) would provide charlie with valuable information by providing a good estimation of whether the firm will need to do short-term borrowing. capital budget cash budget operating budget line item budget
Answers: 3
question
Business, 22.06.2019 12:10
Compute the cost of not taking the following cash discounts. (use a 360-day year. do not round intermediate calculations. input your final answers as a percent rounded to 2 decimal places.)
Answers: 1
question
Business, 22.06.2019 15:30
The school cafeteria can make pizza for approximately $0.30 a slice. the cost of kitchen use and cafeteria staff runs about $200 per day. the pizza den nearby will deliver whole pizzas for $9.00 each. the cafeteria staff cuts the pizza into eight slices and serves them in the usual cafeteria line. with no cooking duties, the staff can be reduced by half, for a fixed cost of $75 per day. should the school cafeteria make or buy its pizzas?
Answers: 3
You know the right answer?
The standards for product V28 call for 8.6 pounds of raw material that costs $19.00 per pound. Last...