subject
Business, 15.04.2020 22:13 jessieeverett432

Gleason Construction enters into a long term fixed price contract to build an office building for $28,000,000. In the first year of the contract Gleason incurs $5,000,000 of cost and the engineers determined that the remaining costs to complete are $18,000,000.

How much gross profit or loss should Gleason recognize irn Year 1 assuming the use of the completed -contract method?

A. $178,571 loss

B, SO profit

C. $5,000,000 loss

D. $2,500,000 profit

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:30
1. gar principles or "the principles"are intended to do what? a. foster an awareness of the hierarchical structure of the organization b. explain the best method of implementing biometric security techniques c. foster an awareness of the importance of good employee training d. foster an awareness of getting upper level management on board in understanding the need to implement an ig program e. foster an awareness of good record keeping principles
Answers: 1
question
Business, 22.06.2019 11:00
What is the correct percentage of texas teachers charged with ethics violations each year?
Answers: 2
question
Business, 22.06.2019 22:40
When immigration adds to the size of the domestic labor pool, which of the following is likely to occur? a. wages decrease. b. productivity increases. c. consumption decreases. d. minimum wage increases.
Answers: 1
question
Business, 23.06.2019 11:50
Iceberg storage, a leading hard drive manufacturer, recently filed for bankruptcy. while most of iceberg's competitors were shifting away from physical data storage devices toward online cloud storage services, iceberg invested most of its retained earnings in the effort to improve its hard drives. once the hard-drive market drastically declined, iceberg storage was unable to capitalize on the new technology. which of the following does this scenario best illustrate a. causal ambiguity b. knowledge diffusion c. social complexity d. path dependence
Answers: 2
You know the right answer?
Gleason Construction enters into a long term fixed price contract to build an office building for $2...
Questions
question
Mathematics, 05.05.2020 10:58
question
Mathematics, 05.05.2020 10:58
question
Mathematics, 05.05.2020 10:58
question
Engineering, 05.05.2020 10:58
Questions on the website: 13722360