You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you have a large budget for the project, you are considering crashing activity A2, which has the potential to shorten the time of A2 by 3 days What do you think about this opportunity?

a. A sood idea, it will reduce the rojet duation by 3 days
b. A bad idea, as A2 is not on the critical path

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 01:30
Iam trying to get more members on my blog. how do i do that?
Answers: 2
question
Business, 22.06.2019 19:30
Kirnon clinic uses client-visits as its measure of activity. during july, the clinic budgeted for 3,250 client-visits, but its actual level of activity was 3,160 client-visits. the clinic has provided the following data concerning the formulas to be used in its budgeting: fixed element per month variable element per client-visitrevenue - $ 39.10personnel expenses $ 35,100 $ 10.30medical supplies 1,100 7.10occupancy expenses 8,100 1.10administrative expenses 5,100 0.20total expenses $ 49,400 $ 18.70the activity variance for net operating income in july would be closest to:
Answers: 1
question
Business, 22.06.2019 22:00
Most economists report the elasticity of demand asa. the absolute value of the actual number.b. a negative number, since price and quantity demanded move in opposite directions.c. a percentage, since both the numerator and denominator are percentages.d. a dollar amount, since we are measuring the change in price.
Answers: 2
question
Business, 22.06.2019 22:10
Scoresby co. uses 6 machine hours and 2 direct labor hours to produce product x. it uses 8 machine hours and 16 direct labor hours to produce product y. scoresby's assembly and finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. how much overhead cost will be charged to the two products? a. product x = $1,440; product y = $2,560 b. product x = $1,760; product y = $4,480 c. product x = $3,200; product y = $9,600 d. product x = $800; product y = $800
Answers: 1
You know the right answer?
You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you ha...
Questions
question
Mathematics, 02.04.2020 01:39
question
Social Studies, 02.04.2020 01:40
Questions on the website: 13722367