A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:
Immediate
Activity Designation Predecessor Time in Days
Break down both machines A None 3
Clean machine 1 B A 3
Clean machine 2 C A 3
Re-set machine 1 D B 4
Re-set machine 2 E C 2
Re-calibrate both machines F D and E 1
Final test G F 1
Using CPM, which activities have slack in this project?
a. A, B, C
b. B, D
c. Only C
d. C, E
e. F, G

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 17:30
Being an expert problem solver is something you're either born with or not. true or false
Answers: 2
question
Business, 22.06.2019 10:00
The solution set for -18 < 5x-3 iso-3х3< xо-3хo3 > x
Answers: 3
question
Business, 22.06.2019 17:30
Gary lives in an area that receives high rainfall and thunderstorms throughout the year. which device would be useful to him to maintain his computer?
Answers: 2
question
Business, 22.06.2019 22:00
"jake’s roof repair has provided the following data concerning its costs: fixed cost per month cost per repair-hour wages and salaries $ 20,900 $ 15.00 parts and supplies $ 7.70 equipment depreciation $ 2,800 $ 0.35 truck operating expenses $ 5,720 $ 1.60 rent $ 4,690 administrative expenses $ 3,850 $ 0.50 for example, wages and salaries should be $20,900 plus $15.00 per repair-hour. the company expected to work 2,600 repair-hours in may, but actually worked 2,500 repair-hours. the company expects its sales to be $47.00 per repair-hour. required: compute the company’s activity variances for may."
Answers: 1
You know the right answer?
A company must perform a maintenance project consisting of seven activities. The activities, their p...
Questions
question
Mathematics, 20.09.2021 03:10
question
English, 20.09.2021 03:10
question
Mathematics, 20.09.2021 03:10
question
Mathematics, 20.09.2021 03:20
Questions on the website: 13722367