A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 15:40
As sales exceed the break‑even point, a high contribution‑margin percentage (a) increases profits faster than does a low contribution-margin percentage (b) increases profits at the same rate as a low contribution-margin percentage (c) decreases profits at the same rate as a low contribution-margin percentage (d) increases profits slower than does a low contribution-margin percentage
Answers: 1
question
Business, 22.06.2019 20:00
Assume the perpetual inventory method is used. 1) the company purchased $12,500 of merchandise on account under terms 2/10, n/30. 2) the company returned $1,200 of merchandise to the supplier before payment was made. 3) the liability was paid within the discount period. 4) all of the merchandise purchased was sold for $18,800 cash. what effect will the return of merchandise to the supplier have on the accounting equation?
Answers: 2
question
Business, 22.06.2019 20:20
Garcia industries has sales of $200,000 and accounts receivable of $18,500, and it gives its customers 25 days to pay. the industry average dso is 27 days, based on a 365-day year. if the company changes its credit and collection policy sufficiently to cause its dso to fall to the industry average, and if it earns 8.0% on any cash freed-up by this change, how would that affect its net income, assuming other things are held constant? a. $241.45b. $254.16c. $267.54d. $281.62e. $296.44
Answers: 2
question
Business, 23.06.2019 02:30
Robert just found out that he is going to be unemployed within a month because his factory has invested in a robotic factory line and his skills are no longer needed. this means that robert is . the gdp within country d has begun to decline. as a result of decreased production, thomas lost his job designing cars. this means that thomas is . raquel has just been offered a job, but she has decided not to take it because she feels her skills merit better pay and a better position. this means that raquel is .
Answers: 1
You know the right answer?
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of...