Business, 06.04.2020 22:35 avahymowitz44

You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule and costs. Based on your review, You should have spent $50,000 to date based on your initial plans and 100 days activities that were based on the schedule.

You have actually spent $60,000 to date and completed activities for 110 days of the scheduled baseline, which should have cost $45,000 based on your initial plans. Budget required for the remaining work to be completed is estimated at $150,000.

Answer the following

PV (Planned Value) =
AC (Actual Cost) =
EV (Earned Value)=
ETC (Estimate to Complete) =
CPI =
SPI =
CV =
SV =
VAC (Variance at Completion) =
EAC (Estimate at Completion) =
TCPI =

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 12:30
Based on an annual disposable income of $40,000, calculate the average amount o money a person would save in japan; in the united states; in france.
Answers: 1
question
Business, 21.06.2019 16:30
How is the architecture career pathway different from the construction pathway? a. architecture involves coordinating with contractors to make sure everyone stays on schedule. b. architecture involves using tools and equipment to build something new. c. architecture involves the design process, considering the function and safety of the project. d. architecture involves evaluating the work of contractors and employees.
Answers: 1
question
Business, 21.06.2019 23:30
Actual usage for the year by the marketing department was 70,000 copies and by the operations department was 330,000 copies. if a dual-rate cost-allocation method is used, what amount of copying facility costs will be budgeted for the operations department?
Answers: 2
question
Business, 22.06.2019 11:20
Aborrower takes out a 30-year adjustable rate mortgage loan for $200,000 with monthly payments. the first two years of the loan have a "teaser" rate of 4%, after that, the rate can reset with a 5% annual payment cap. on the reset date, the composite rate is 6%. what would the year 3 monthly payment be?
Answers: 3
You know the right answer?
You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, yo...
Questions
question
Engineering, 19.02.2021 03:50
question
Mathematics, 19.02.2021 03:50
question
Mathematics, 19.02.2021 03:50
question
English, 19.02.2021 03:50
question
Mathematics, 19.02.2021 03:50
Questions on the website: 13722361