Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.

PV = $23,000EV = $20,000AC = $25,000BAC = $120,000What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:30
Issued to the joint planning and execution community (jpec) initiates the development of coas; it also requests that the supported ccdr submit a commander's estimate of the situation with a recommended coa to resolve the situation (joint force command and staff participation in the joint operation planning and execution system, page 10)
Answers: 2
question
Business, 22.06.2019 12:00
Suppose there are three types of consumers who attend concerts at your university’s performing arts center: students, staff, and faculty. each of these groups has a different willingness to pay for tickets; within each group, willingness to pay is identical. there is a fixed cost of $1,000 to put on a concert, but there are essentially no variable costs. for each concert: i. there are 140 students willing to pay $20. (ii) there are 200 staff members willing to pay $35. (iii) there are 100 faculty members willing to pay $50. a) if the performing arts center can charge only one price, what price should it charge? what are profits at this price? b) if the performing arts center can price discriminate and charge two prices, one for students and another for faculty/staff, what are its profits? c) if the performing arts center can perfectly price discriminate and charge students, staff, and faculty three separate prices, what are its profits?
Answers: 1
question
Business, 22.06.2019 12:40
Alarge tank is filled to capacity with 500 gallons of pure water. brine containing 2 pounds of salt per gallon is pumped into the tank at a rate of 5 gal/min. the well-mixed solution is pumped out at the same rate. find the number a(t) of pounds of salt in the tank at time t.
Answers: 3
question
Business, 22.06.2019 12:50
Jallouk corporation has two different bonds currently outstanding. bond m has a face value of $50,000 and matures in 20 years. the bond makes no payments for the first six years, then pays $2,100 every six months over the subsequent eight years, and finally pays $2,400 every six months over the last six years. bond n also has a face value of $50,000 and a maturity of 20 years; it makes no coupon payments over the life of the bond. the required return on both these bonds is 10 percent compounded semiannually. what is the current price of bond m and bond n?
Answers: 3
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Mathematics, 20.04.2021 18:50
question
Mathematics, 20.04.2021 18:50
question
Spanish, 20.04.2021 18:50
question
Mathematics, 20.04.2021 18:50
Questions on the website: 13722362