Metal frames for kick scooters are manufactured in two steps: Stamping and assembly. Each frame is made up of three pieces: one unit of part A and two units of part B.

The parts are fabricated by a single stamping machine that requires a set up time of 90 minutes switching between two part types. Once the machine is set up, the activity time for parts, regardless of type, is 30 seconds each piece. Currently, the stamping machine rotates its production between one batch of 120 part A’s and 240 part B’s. Completed parts move only when the entire batch is produced.

At assembly, parts are assembled manually to form the finished products. The three parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 12 workers in assembly. There is sufficient demand to sell every scooter the system can make.

At the current batch sizes, what is the process capacity in units per hour? Choose the answer below that is closest to the correct answer. A unit refers to a complete scooter frame (i. e. one part A and two parts B)

a. 1 unit/ hr
b. 5 units/ hr
c. 10 units/ hr
d. 20 units/ hr
e. 24 units/ hr
f. 30 units/ hr
g. 40 units/ hr

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:30
Acompany factory is considered which type of resource a.land b.physical capital c.labor d.human capital
Answers: 2
question
Business, 22.06.2019 19:40
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
question
Business, 22.06.2019 20:10
The gilbert instrument corporation is considering replacing the wood steamer it currently uses to shape guitar sides. the steamer has 6 years of remaining life. if kept,the steamer will have depreciaiton expenses of $650 for five years and $325 for the sixthyear. its current book value is $3,575, and it can be sold on an internet auction site for$4,150 at this time. if the old steamer is not replaced, it can be sold for $800 at the endof its useful life. gilbert is considering purchasing the side steamer 3000, a higher-end steamer, whichcosts $12,000 and has an estimated useful life of 6 years with an estimated salvage value of$1,500. this steamer falls into the macrs 5-year class, so the applicable depreciationrates are 20.00%, 32.00%, 19.20%, 11.52%, 11.52%, and 5.76%. the new steamer is fasterand allows for an output expansion, so sales would rise by $2,000 per year; the newmachine's much greater efficiency would reduce operating expenses by $1,900 per year.to support the greater sales, the new machine would require that inventories increase by$2,900, but accounts payable would simultaneously increase by $700. gilbert's marginalfederal-plus-state tax rate is 40%, and its wacc is 15%.a. should it replace the old steamer? b. npv of replace = $2,083.51
Answers: 2
question
Business, 22.06.2019 23:40
Robert is a district manager who oversees several store managers in a national chain of restaurants. robert reports directly to the vice president of stores and marketing, a member of top management. robert is a middle manager.t/f
Answers: 2
You know the right answer?
Metal frames for kick scooters are manufactured in two steps: Stamping and assembly. Each frame is m...
Questions
Questions on the website: 13722359