Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.33 million. The fixed asset falls into the 3-year MACRS class (MACRS schedule). The project is estimated to generate $1,735,000 in annual sales, with costs of $640,000. The project requires an initial investment in net working capital of $300,000, and the fixed asset will have a market value of $255,000 at the end of the project.

a. If the tax rate is 25 percent, what is the project’s Year 0 net cash flow? Year 1? Year 2? Year 3? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers in dollars, not millions of dollars, rounded to two decimal places, e. g., 1,234,567.89.)

b. If the required return is 9 percent, what is the project's NPV? (Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to two decimal places, e. g., 1,234,567.89.)

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 15:40
Brandt enterprises is considering a new project that has a cost of $1,000,000, and the cfo set up the following simple decision tree to show its three most likely scenarios. the firm could arrange with its work force and suppliers to cease operations at the end of year 1 should it choose to do so, but to obtain this abandonment option, it would have to make a payment to those parties. how much is the option to abandon worth to the firm?
Answers: 1
question
Business, 23.06.2019 02:50
Three years ago, stock tek purchased some five-year macrs property for $82,600. today, it is selling this property for $31,500. how much tax will the company owe on this sale if the tax rate is 34 percent? the macrs allowance percentages are as follows, commencing with year 1: 20.00, 32.00, 19.20, 11.52, 11.52, and 5.76 percent.
Answers: 1
question
Business, 23.06.2019 03:00
What are the weak points of economic costs that are part of a free enterprise economy?
Answers: 1
question
Business, 23.06.2019 12:30
Food goblin supermarkets use both cashiers and baggers to serve customers at check out. during the first 6 hours of each workday (monday-friday), 3 cashiers and 2 baggers serve approximately 23 customers per hour. a cashier and a bagger who require approximately 4 minutes at checkout and 3 minutes at bagging serve each customer. a. how many employees should food goblin supermarket schedule if it requires a 12 percent capacity cushion? food goblin supermarket should schedule nothing cashier(s). (enter your response rounded up to the nearest whole number.)
Answers: 1
You know the right answer?
Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial f...
Questions
question
Health, 20.04.2021 20:20
question
Mathematics, 20.04.2021 20:20
question
Mathematics, 20.04.2021 20:20
question
Mathematics, 20.04.2021 20:20
question
Mathematics, 20.04.2021 20:20
question
Mathematics, 20.04.2021 20:20
Questions on the website: 13722360