A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost. If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then

Select one:

a. the FCAC is greater than the TBC.
b. the FCAC is less than the TBC.
c. the FCAC cannot be calculated with the values given.
d. additional information is needed to predict the FCAC.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:00
Which statement is true of both presidential and parliamentary systems of government? a. the executive branch operates independently from the legislative branch. b. the members of the legislative branch are directly elected by the people. c. the head of government is chosen by members of his or her political party. d. the head of government is directly elected by the people
Answers: 1
question
Business, 23.06.2019 10:00
Vincent enjoys investing his money in ways that can generate a return. he realizes that also a chance that his investment will decrease in value. this chance is known as a. opportunity cost b. risk c. recession d. deterioration
Answers: 1
question
Business, 23.06.2019 11:00
Advertisers like online advertising because
Answers: 1
question
Business, 23.06.2019 13:30
the social-cultural environment a firm operates in is constantly changing, and having a significant impact on marketing strategies. the change is so rapid and immense that some firms have created a new position in the organization to handle this change. which title best describes the new position described in the scenario?
Answers: 3
You know the right answer?
A third method for determining the forecasted cost at completion is to re-estimate the costs for all...
Questions
question
History, 02.09.2019 11:00
question
Mathematics, 02.09.2019 11:00
Questions on the website: 13722360