A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
Partnerships are the most common type of business firms in the world. t/f
Answers: 3
question
Business, 22.06.2019 18:10
Find the zeros of the polynomial 5 x square + 12 x + 7 by factorization method and verify the relation between zeros and coefficient of the polynomials
Answers: 1
question
Business, 22.06.2019 19:00
Why is accountability important in managing safety
Answers: 2
question
Business, 22.06.2019 20:00
If an investment has 35 percent more nondiversifiable risk than the market portfolio, its beta will be:
Answers: 1
You know the right answer?
A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000....
Questions
question
Mathematics, 20.04.2021 19:20
question
Biology, 20.04.2021 19:20
question
English, 20.04.2021 19:20
Questions on the website: 13722367