subject
Business, 16.03.2020 17:38 CameronVand21

Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of 41. Alex is one of the production workers and he works eight hours a day, five days a week. Each order is one window and each window takes 55 minutes.

What is the cycle time for an order?

A. 6.86 minutes per window
B12.5minutes per window
C.5minutes per window
D. 250minutes per window

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:50
Which of the following statements is not correct? 1) trade allows for specialization. 2) trade has the potential to benefit all nations. 3) trade allows nations to consume outside of their production possibilities curves. 4) absolute advantage is the driving force of specialization.
Answers: 3
question
Business, 22.06.2019 06:30
Double corporation acquired all of the common stock of simple company for
Answers: 2
question
Business, 22.06.2019 07:40
(a) what was the opportunity cost of non-gm food for many buyers before 2008? (b) why did they prefer the alternative? (c) what was the opportunity cost in 2008? (d) why did it change?
Answers: 3
question
Business, 22.06.2019 09:40
Alpha industries is considering a project with an initial cost of $8 million. the project will produce cash inflows of $1.49 million per year for 8 years. the project has the same risk as the firm. the firm has a pretax cost of debt of 5.61 percent and a cost of equity of 11.27 percent. the debt–equity ratio is .60 and the tax rate is 35 percent. what is the net present value of the project?
Answers: 1
You know the right answer?
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from...