Digital Eye must design an assembly line to produce a new line of slim digital cameras. Assembling a single camera required the completion of nine distinct tasks, and information about each of these tasks is provided below:
Task Immediate Predecessors Task Duration (sec.)
A None 10
B A 30
C A 25
D B 18
E B 5
F B 17
G D, E 37
H C, F 30
I H 12
This assembly line operates 8 hours per day to produce 576 digital cameras daily. Digital Eye uses the LPT rule to create the design.
1. What is the cycle time of Digital Eye's assembly line, in seconds?
2. How many workstations are required by this design and what tasks will be done at which workstations?
3. Which workstation enjoys the maximum idle time? How efficient is this design?
4. How does the actual number of workstations required by this design compare to its theoretical minimum number of workstations?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 17:40
Carlos would like to start saving for his son’s college expenses. which type of savings account should carlos open? ida money market 529 plan basic savings account
Answers: 2
question
Business, 21.06.2019 23:00
The monthly payment m of a loan of amount p for y years with an interest rate r can be calculated by the formula: m = p(r/12) 1 â’ (1 + r/12)â’12y calculate the monthly payment and the cummulative total payment for a $100,000 loan with an interest rate of 4.85% if taken out for 10 years, for 11 years, etc., up to a 30 year term. display the results in a three-column table where the first column is the number of years, the second is the monthly payment, and the third is the cummulative total payment. note: use format bank; for this problem. also, remember to represent the interest rate as a decimal (e.g. 0.0485) 2. a torus-shaped water tube is designed to have a volume of 8, 000in3 . the volume of the tube, v , and its surface area, s, are given by: v = 1 4 ď€ 2 (a + b)(b â’ a) 2 s = ď€ 2 (b 2 â’ a 2 ) if a = kb, determine s, a, and b for k = 0.2, 0.3, 0.7. display the results in a table
Answers: 1
question
Business, 22.06.2019 18:30
You should typically prepare at least questions for the people who will host you during a job shadow. a. 3 b. 4 c. 5 d. 2
Answers: 1
question
Business, 22.06.2019 23:20
Nnette henri is paid an hourly wage of $8.90 for a 32-hour workweek of 4 days, 8 hours daily. for any work on the fifth day and on saturdays, she is paid one and one-half times her regular hourly rate. during a certain week, in addition to her regular 32 hours, henri worked 6 hours on the fifth day and 5 hours on saturday. for this workweek, henri’s total earnings are:
Answers: 1
You know the right answer?
Digital Eye must design an assembly line to produce a new line of slim digital cameras. Assembling a...
Questions
question
Mathematics, 12.03.2020 02:29
question
Mathematics, 12.03.2020 02:29
Questions on the website: 13722363