A job had an observed time of 10 minutes, a performance rating of .90, and an allowance factor of 20 percent of job time. Twenty-five cycles were timed. Standard time for the job in minutes is:

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:00
Sarah borrowed $16,500 on may 23 with interest due on september 3. if the interest rate is 9%, find the interest on the loan using exact interest and ordinary interest.
Answers: 2
question
Business, 22.06.2019 01:30
At the end of the week, carla receives her paycheck and goes directly to the bank after work to make a deposit into her savings account. the bank keeps the required reserve and then loans out the remaining balance to a qualified borrower named malik as a portion of his small business loan. malik uses the loan to buy a tractor for his construction business and makes small monthly payments to the bank to payback the principal balance plus interest on the loan. the bank profits from a portion of the interest payment received and also passes some of the interest back to carla in the form of an interest payment to her savings account. in this example, the bank is acting
Answers: 1
question
Business, 22.06.2019 08:00
How do communism and socialism differ in terms of the role that government plays in the economy ?
Answers: 1
question
Business, 22.06.2019 10:30
How are interest rates calculated by financial institutions? financial institutions generally calculate interest as (1) interest or (.
Answers: 1
You know the right answer?
A job had an observed time of 10 minutes, a performance rating of .90, and an allowance factor of 20...
Questions
question
Mathematics, 04.04.2020 14:59
Questions on the website: 13722363