During 2020, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available.

2014 2015 2016
Costs incurred to date $400,000 $825,000 $1070,000
Estimated costs to complete 600,000 275,000 0
Billings to date 300,000 900,000 1600,000
Collections to date 270,000 810,000 14,25000

Required:
a. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
b. Prepare all necessary journal entries for 2015
c. Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:20
Overspeculation and a decrease in consumer confidence are both leading factors of: ?
Answers: 1
question
Business, 22.06.2019 17:30
According to management education expert ashok rao, companies can increase their profitability by through careful inventory management. a. 5% to 10% b. 10% to 25% c. 20% to 50% d. 75%
Answers: 1
question
Business, 22.06.2019 20:00
Suppose a country's productivity last year was 84. if this country's productivity growth rate of 5 percent is to be maintained, this means that this year's productivity will have to be:
Answers: 2
question
Business, 23.06.2019 02:30
Do you think it ethical and appropriate for marshall to have used himself as a test subject and swallowed a sample of helicobacter pylori? what precautions did he take? would you do it? why or why not?
Answers: 1
You know the right answer?
During 2020, Nilsen Company started a construction job with a contract price of $1,600,000. The job...
Questions
question
Mathematics, 11.12.2020 09:20
question
Mathematics, 11.12.2020 09:20
question
Mathematics, 11.12.2020 09:20
Questions on the website: 13722367