Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
2020 2021 2022
Costs to date 270,000 450,000 610,000
Estimated costs to complete 330,000 150,000 0
Progress billings to date 270,000 550,000 900,000
Cash collected to date 240,000 500,000 900,000

(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 07:00
Imagine you own an established startup with growing profits. you are looking for funding to greatly expand company operations. what method of financing would be best for you?
Answers: 2
question
Business, 22.06.2019 08:10
The sec has historically raised questions regarding the independence of firms that derive a significant portion of their total revenues from one audit client or group of clients because the sec staff believes this situation causes cpa firms to
Answers: 3
question
Business, 22.06.2019 20:10
Suppose the production function in an economy is y = k0.5l0.5, where k is the amount of capital and l is the amount of labor. the economy begins with 64 units of capital and 16 units of labor. use a calculator and equations in the chapter to find a numerical answer to each of the following questions. what are the wage and the rental price of capital? the wage is equal to unit(s) of output and the rental price of capital is equal to unit(s) of output.
Answers: 1
question
Business, 22.06.2019 21:10
Skychefs, inc. prepares in-flight meals for a number of major airlines. one of the company's products is grilled salmon in dill sauce with baby new potatoes and spring vegetables. during the most recent week, the company prepared 4000 of these meals using 960 direct labor hours. the company paid these direct labor workers a total of $19,200 for this work, or $20.00 per hour. according to standard cost card for this meal, it should require 0.25 direct labour-hours at a cost of $19.75 per hour.1. what is the standard labor-hours allowed (sh) to prepare 4,000 meals? 2. what is the standard labor cost allowed (sh x sr) to prepare 4,000 meals? 3. what is the labor spending variance? 4. what is the labor rate variance and the labor efficiency variance?
Answers: 3
You know the right answer?
Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a park...
Questions
question
Mathematics, 21.09.2020 05:01
question
Mathematics, 21.09.2020 05:01
question
Mathematics, 21.09.2020 05:01
Questions on the website: 13722362