Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $65,000
EV = $58,000
AC = $68,000
BAC = $155,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Use the SPI to estimate how long it will take to finish this project.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 08:00
Interest is credited to a fixed annuity no lower than the variable contract rate contract guaranteed rate current rate of inflation prime rate
Answers: 2
question
Business, 22.06.2019 15:30
In 2015, lori assigned a paid-up whole life insurance policy to an irrevocable life insurance trust (ilit) for the benefit of her three children. the ilit contained a crummey provision for the benefit of each child. at the time of the transfer, the whole life insurance policy was valued at $200,000, and since lori had not made any other taxable gifts during her lifetime, she did not owe any gift tax. lori died in 2016, and the face value of the whole life insurance policy of $2,000,000 was paid to the ilit. regarding this transfer, how much is included in lori’s gross estate at her death?
Answers: 1
question
Business, 22.06.2019 19:30
Nextdoor is an instant messaging application for smartphones. new smartphone users find it easier to connect with friends and relatives through this mobile app when compared to other similar instant messaging applications. hence, it has the largest user base in the industry. thus, nextdoor app's value has increased primarily due to itsa. learning curve effects. b. economies of scale. c. economies of scope. d. network effects.
Answers: 2
question
Business, 22.06.2019 23:10
Until recently, hamburgers at the city sports arena cost $4.70 each. the food concessionaire sold an average of 13 comma 000 hamburgers on game night. when the price was raised to $5.40, hamburger sales dropped off to an average of 6 comma 000 per night. (a) assuming a linear demand curve, find the price of a hamburger that will maximize the nightly hamburger revenue. (b) if the concessionaire had fixed costs of $1 comma 500 per night and the variable cost is $0.60 per hamburger, find the price of a hamburger that will maximize the nightly hamburger profit.
Answers: 1
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Mathematics, 05.10.2019 08:00
Questions on the website: 13722363