"The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?"

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
Jurvin enterprises is a manufacturing company that had no beginning inventories. a subset of the transactions that it recorded during a recent month is shown below. $76,700 in raw materials were purchased for cash. $71,400 in raw materials were used in production. of this amount, $66,300 was for direct materials and the remainder was for indirect materials. total labor wages of $151,700 were incurred and paid. of this amount, $134,300 was for direct labor and the remainder was for indirect labor. additional manufacturing overhead costs of $126,300 were incurred and paid. manufacturing overhead of $126,800 was applied to production using the company's predetermined overhead rate. all of the jobs in process at the end of the month were completed. all of the completed jobs were shipped to customers. any underapplied or overapplied overhead for the period was closed to cost of goods sold.required: 1. post the above transactions to t-accounts.2. determine the cost of goods sold for the period.
Answers: 1
question
Business, 22.06.2019 17:30
You should do all of the following before a job interview except
Answers: 2
question
Business, 22.06.2019 20:20
Gamegirl inc., has the following transactions during august. august 6 sold 76 handheld game devices for $230 each to ds unlimited on account, terms 2/10, net 60. the cost of the 76 game devices sold, was $210 each. august 10 ds unlimited returned six game devices purchased on 6th august since they were defective. august 14 received full amount due from ds unlimited. required: prepare the transactions for gamegirl, inc., assuming the company uses a perpetual inventory syste
Answers: 2
question
Business, 23.06.2019 01:30
The stock market is -the section of the newspaper where you learn how much a stock is worth -a place where you buy and sell stock -an organized way for people to buy and sell stocks -the same as a brokerage firm
Answers: 1
You know the right answer?
"The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to ta...
Questions
question
Social Studies, 27.09.2019 19:30
question
Chemistry, 27.09.2019 19:30
question
Mathematics, 27.09.2019 19:30
question
Mathematics, 27.09.2019 19:30
Questions on the website: 13722360