If the best operating level of a piece of equipment is at a rate of 400 units per hour and the actual output during an hour is 300 units, which of the following is the capacity cushion?A. 25 percent
B. 100 units per hour
C. 75 percent
D. 125 percent
E. 133 percent

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:50
Last year, western corporation had sales of $5 million, cost of goods sold of $3 million, operating expenses of $175,000 and depreciation of $125,000. the firm received $40,000 in dividend income and paid $200,000 in interest on loans. also, western sold stock during the year, receiving a $40,000 gain on stock owned 6 years, but losing $60,000 on stock owned 4 years. what is the firm's tax liability?
Answers: 2
question
Business, 22.06.2019 09:00
Harry is 25 years old with a 1.55 rating factor for his auto insurance. if his annual base premium is $1,012, what is his total premium? $1,568.60 $2,530 $1,582.55 $1,842.25
Answers: 3
question
Business, 22.06.2019 10:10
At the end of year 2, retained earnings for the baker company was $3,550. revenue earned by the company in year 2 was $3,800, expenses paid during the period were $2,000, and dividends paid during the period were $1,400. based on this information alone, retained earnings at the beginning of year 2 was:
Answers: 1
question
Business, 22.06.2019 11:50
Stocks a, b, and c are similar in some respects: each has an expected return of 10% and a standard deviation of 25%. stocks a and b have returns that are independent of one another; i.e., their correlation coefficient, r, equals zero. stocks a and c have returns that are negatively correlated with one another; i.e., r is less than 0. portfolio ab is a portfolio with half of its money invested in stock a and half in stock b. portfolio ac is a portfolio with half of its money invested in stock a and half invested in stock c. which of the following statements is correct? a. portfolio ab has a standard deviation that is greater than 25%.b. portfolio ac has an expected return that is less than 10%.c. portfolio ac has a standard deviation that is less than 25%.d. portfolio ab has a standard deviation that is equal to 25%.e. portfolio ac has an expected return that is greater than 25%.
Answers: 3
You know the right answer?
If the best operating level of a piece of equipment is at a rate of 400 units per hour and the actua...
Questions
question
History, 30.11.2020 19:40
question
Mathematics, 30.11.2020 19:40
question
Mathematics, 30.11.2020 19:40
question
History, 30.11.2020 19:40
question
Social Studies, 30.11.2020 19:40
question
Mathematics, 30.11.2020 19:40
question
Mathematics, 30.11.2020 19:40
Questions on the website: 13722363