Consider a process consisting of three resources. Assume there exists unlimited demand for the product.
Resource 1 has a processing time of 5 minutes per unit
Resource 2 has a processing time of 2 minutes per unit.
Resource 3 has a processing time of 3 minutes per unit.
All three resources are staffed by one worker and each worker gets paid $ 13 per hour. Use two decimals where applicable.
a. What is the cost of direct labor? $ dollars per unit
b. What is the labor content? minutes per unit
c. How much idle time does the worker at resource 3 have per unit? minutes per unit
d. What is the average labor utilization? percent
e. Assuming the demand rate is 29 units per hour, what is the takt time? minutes per unit
f. Assuming the demand rate is 29 units per hour, what is the target manpower?
Answers: 2
Business, 22.06.2019 01:00
Azster inc. recorded sales revenue for the year that ended december 31, 2014 as $67,000. interest revenue of $5,300 and expenses of $14,000 were also recorded for the same period. what is aster’s net profit or loss?
Answers: 3
Business, 22.06.2019 01:30
How will firms solve the problem of an economic surplus a. decrease prices to the market equilibrium price b. decrease prices so they are below the market equilibrium price c.increase prices
Answers: 3
Business, 22.06.2019 03:30
When the federal reserve buys and sells bonds to member banks, it is called a. monetary policy b. reserve ratio c. interest rate adjustment d. open market operations
Answers: 2
Business, 22.06.2019 10:30
Jack manufacturing company had beginning work in process inventory of $8,000. during the period, jack transferred $34,000 of raw materials to work in process. labor costs amounted to $41,000 and overhead amounted to $36,000. if the ending balance in work in process inventory was $12,000, what was the amount transferred to finished goods inventory?
Answers: 2
Consider a process consisting of three resources. Assume there exists unlimited demand for the produ...
Social Studies, 18.08.2019 23:50
Mathematics, 18.08.2019 23:50
Mathematics, 18.08.2019 23:50
Business, 18.08.2019 23:50
Social Studies, 18.08.2019 23:50
Geography, 18.08.2019 23:50
Mathematics, 18.08.2019 23:50
Mathematics, 18.08.2019 23:50
English, 18.08.2019 23:50
Mathematics, 18.08.2019 23:50
English, 18.08.2019 23:50
Social Studies, 18.08.2019 23:50