subject
Business, 28.02.2020 03:32 jessica94866

The purpose of doing a new baseline is
(A) to complete the change approval process
(B) to assess the net impact of a change on the scope, schedule and/or budget for the project
(C) to calculate Earned Value statistics on the project
(D) To document the most up-to-date plans for scope, schedule and budget on the project with all changes applied.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:40
Uppose stanley's office supply purchases 50,000 boxes of pens every year. ordering costs are $100 per order and carrying costs are $0.40 per box. moreover, management has determined that the eoq is 5,000 boxes. the vendor now offers a quantity discount of $0.20 per box if the company buys pens in order sizes of 10,000 boxes. determine the before-tax benefit or loss of accepting the quantity discount. (assume the carrying cost remains at $0.40 per box whether or not the discount is taken.)
Answers: 1
question
Business, 22.06.2019 08:10
Bakery has bought 250 pounds of muffin dough. they want to make waffles or muffins in half-dozen packs out of it. half a dozen of muffins requires 1 lb of dough and a pack of waffles uses 3/4 lb of dough. it take bakers 6 minutes to make a half-dozen of waffles and 3 minutes to make a half-dozen of muffins. their profit will be $1.50 on each pack of waffles and $2.00 on each pack of muffins. how many of each should they make to maximize profit, if they have just 20 hours to do everything?
Answers: 3
question
Business, 22.06.2019 09:00
You speak to a business owner that is taking in almost $2000 in revenue each month. the owner still says that they are having trouble keeping the doors open. how can that be possible? use the terms of revenue, expenses and profit/loss in your answer
Answers: 3
question
Business, 22.06.2019 20:00
If an investment has 35 percent more nondiversifiable risk than the market portfolio, its beta will be:
Answers: 1
You know the right answer?
The purpose of doing a new baseline is
(A) to complete the change approval process
(B)...
Questions
Questions on the website: 13722363