Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS
At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information:
Job 86 Job 87
Direct materials $4,800 $1,600
Direct labor 1,200 3,000
Applied overhead 888 2,220
Balance, March 1 $6,888 $6,820
During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to the four jobs during the month of March:
Job 86 Job 87 Job 88 Job 89
Direct materials $3,000 $7,000 $2,100 $1,500
Direct labor 800 6,000 900 500
At the end of March, Jobs 86, 87, and 89 were completed. Only Job 87 was sold. On March 1, the balance in Finished Goods was zero.
Required:
1. Calculate the overhead rate based on direct labor cost.
$ %
2. Prepare a brief job-order cost sheet for the four jobs. Show the balance as of March 1 as well as direct materials and direct labor added in March. Apply overhead to the four jobs for the month of March, and show the ending balances.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:00
The following accounts appeared in recent financial statements of delta air lines. identify each account as either a balance sheet account or an income statement account. for each balance sheet account, identify it as an asset, a liability, or stockholders' equity. for each income statement account, identify it as a revenue or an expense. item financial statement type of account accounts payable balance sheet advanced payments for equipment balance sheet air traffic liability balance sheet aircraft fuel (expense) income statement aircraft maintenance (expense) income statement aircraft rent (expense) income statement cargo revenue income statement cash balance sheet contract carrier arrangements (expense) income statement flight equipment balance sheet frequent flyer (obligations) balance sheet fuel inventory balance sheet landing fees (expense) income statement parts and supplies inventories balance sheet passenger commissions (expense) income statement passenger revenue income statement prepaid expenses income statement taxes payable balance sheet
Answers: 1
question
Business, 22.06.2019 01:20
What cylinder head operation is the technician performing in this figure?
Answers: 1
question
Business, 22.06.2019 17:50
Variable rate cd’s = $90 treasury bills = $150 discount loans = $20 treasury notes = $100 fixed rate cds = $160 money market deposit accts. = $140 savings deposits = $90 fed funds borrowing = $40 variable rate mortgage loans $140 demand deposits = $40 primary reserves = $50 fixed rate loans = $210 fed funds lending = $50 equity capital = $120 a. develop a balance sheet from the above data. be sure to divide your balance sheet into rate-sensitive assets and liabilities as we did in class and in the examples. b. perform a standard gap analysis and a duration analysis using the above data if you have a 1.15% decrease in interest rates and an average duration of assets of 5.4 years and an average duration of liabilities of 3.8 years. c. indicate if this bank will remain solvent after the valuation changes. if so, indicate the new level of equity capital after the valuation changes. if not, indicate the amount of the shortage in equity capital.
Answers: 3
question
Business, 22.06.2019 22:50
Wendy made her career planning timeline in 2010. in what year should wendy's timeline start? a. 2013 o b. 2012 oc. 2010 o d. 2011
Answers: 2
You know the right answer?
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, a...
Questions
question
Mathematics, 06.07.2019 02:40
question
Mathematics, 06.07.2019 02:40
Questions on the website: 13722363