A project costs $91,000 today and is expected to generate cash flows of $11,000 per year for the next 20years. The firm has a cost of capital of 8 percent. Should this project be accepted, and why?

A. Yes, the project should be accepted since it has a NPV = $15,391.23.
B. Yes, the project should be accepted since it has a NPV = $13,610.89.
C. Yes, the project should be accepted since it has a NPV = $16,999.62.
D. None of these answers is correct.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:10
Braverman company has two manufacturing departments—finishing and fabrication. the predetermined overhead rates in finishing and fabrication are $18.00 per direct labor-hour and 110% of direct materials cost, respectively. the company’s direct labor wage rate is $16.00 per hour. the following information pertains to job 700: finishing fabrication direct materials $ 410 $ 60 direct labor $ 128 $ 48 required: 1. what is the total manufacturing cost assigned to job 700? 2. if job 700 consists of 15 units, what is the unit product cost for this job?
Answers: 1
question
Business, 22.06.2019 02:30
Question 1 which of the following tasks use your roommate as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough spoon cookies onto the tray unload the cookies from the oven pack the cookies 1 points question 2 which of the following tasks use the tray(s) as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough bake the cookies cool the cookies accept payment 1 points question 3 determine the task time for the following tasks. fill integer numbers into the blank (e.g., 5 rather than 5.0) wash and mixing the dough: minute(s)/order spoon cookies onto the tray: minute(s)/order set up timer: minute(s)/order bake: minute(s)/order cool the cookies: minute(s)/order pack the cookies: minute(s)/order accept payment: minute(s)/order 2 points question 4 q4: determine the cycle time for the following resources. fill integer numbers into the blank (e.g., 5 rather than 5.0) kristen (you): minute(s) roommate: minute(s) oven: minute(s) 2 points question 5 what is the capacity rate (in orders/hour) of the roommate? 1 points question 6 what is the capacity rate (in orders/hour) of the whole process? 2 points question 7 how long (in minutes) it takes to process the first order?
Answers: 3
question
Business, 22.06.2019 04:00
Wallis company manufactures only one product and uses a standard cost system. the company uses a predetermined plantwide overhead rate that relies on direct labor-hours as the allocation base. all of the company's manufacturing overhead costs are fixed—it does not incur any variable manufacturing overhead costs. the predetermined overhead rate is based on a cost formula that estimated $2,886,000 of fixed manufacturing overhead for an estimated allocation base of 288,600 direct labor-hours. wallis does not maintain any beginning or ending work in process inventory.
Answers: 2
question
Business, 22.06.2019 11:00
Which statement best describes the variety of workplaces commonly found in the health science career cluster? a. workplaces in this cluster include healthcare facilities such as hospitals, physician offices, and clinics. b. workplaces in this cluster include healthcare facilities, laboratories, and other environments such as offices or homes. c . workplaces in this cluster include nonprofit hospitals, government-run clinics, and private physicians' offices. d. workplaces in this cluster include private and nonprofit hospitals and clinics, and dentists' offices.
Answers: 1
You know the right answer?
A project costs $91,000 today and is expected to generate cash flows of $11,000 per year for the nex...
Questions
question
Mathematics, 16.01.2020 17:31
question
Mathematics, 16.01.2020 17:31
question
Mathematics, 16.01.2020 17:31
question
Chemistry, 16.01.2020 17:31
question
Mathematics, 16.01.2020 17:31
Questions on the website: 13722367