In making a forward pass through a network, activities l, m, and p are immediate predecessors for activity t, which has an activity time of 7. the early start times for activities l, m, and p are 22, 17, and 27, respectively. the early finish times for activities l, m, and p are 29, 27, and 33, respectively. what is the early finish time for activity t?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:50
You own 2,200 shares of deltona hardware. the company has stated that it plans on issuing a dividend of $0.42 a share at the end of this year and then issuing a final liquidating dividend of $2.90 a share at the end of next year. your required rate of return on this security is 16 percent. ignoring taxes, what is the value of one share of this stock to you today?
Answers: 1
question
Business, 22.06.2019 16:40
An electronics store is running a promotion where for every video game purchased, the customer receives a coupon upon checkout to purchase a second game at a 50% discount. the coupons expire in one year. the store normally recognized a gross profit margin of 40% of the selling price on video games. how would the store account for a purchase using the discount coupon?
Answers: 3
question
Business, 22.06.2019 21:50
The third program provides families with $50 in food stamps each week, redeemable for both perishable and nonperishable food. the fourth policy instead provides a family with a box of nonperishable foods each week, worth $50. use two graphs to illustrate that a family may be indifferent between the two programs, but will never prefer the $50 box of nonperishable foods over the $50 in food stamps. state your answer and use a consumer choice model for perishable food and nonperishable food to graphically justify your choice.
Answers: 1
question
Business, 23.06.2019 10:00
Vincent enjoys investing his money in ways that can generate a return. he realizes that also a chance that his investment will decrease in value. this chance is known as a. opportunity cost b. risk c. recession d. deterioration
Answers: 1
You know the right answer?
In making a forward pass through a network, activities l, m, and p are immediate predecessors for ac...
Questions
question
Mathematics, 24.01.2020 00:31
question
Mathematics, 24.01.2020 00:31
Questions on the website: 13722367