Activity a has a duration of 3 days and begins on the morning of monday the 4th. the successor activity, b, has a finish-to-start relationship with a. the finish-to-start relationship has lag of 3 days, and activity b has a duration of 5 days. in case sunday is a nonworking day what can be determined from this data?
a. total elapsed days (completing both activities) is 7 days
b. activity b will be completed by the end of day on thursday, 14th
c. activity b will be completed by the end of day on friday, 15th.
d. activity b will be completed by the end of day on tuesday, 12th

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 12:00
In mexico, many garment or sewing shops found they could entice many young people to work for them if they offered clean, air conditioned work areas with high-quality locker rooms to clean up in after the work day. typically, traditional garment shops had to offer to get workers to apply for the hard, repetitive, and somewhat dangerous work. a. benchmark competitive wages b.compensating differentials c. monopoly wages d. wages based on human capital development of each employee
Answers: 3
question
Business, 23.06.2019 02:20
The director of the federal trade commission (ftc) bureau of consumer protection warned that the agency would bring enforcement action against small businesses that select one: a. failed to inform the public about network failures in a timely manner b. failed to transmit sensitive data c. did not report security breaches to law enforcement d. lacked adequate policies and procedures to protect consumer data.
Answers: 2
question
Business, 23.06.2019 02:40
This year, druehl, inc., will produce 60 comma 000 hot water heaters at its plant in delaware, in order to meet expected global demand. to accomplish this, each laborer at the plant will work 200 hours per month. if the labor productivity at the plant is 0.25 hot water heaters per labor hour, how many laborers are employed at the plant? number of laborers employed by the plant = nothing laborers (round your answer to the nearest whole number).
Answers: 2
question
Business, 23.06.2019 10:00
Top flight is a commuter airline service that provides short flights to neighboring citles around houston, texas. to determine the quantity of planes it will purchase, top flight needs to examine the for its flights at the prices it intends to charge and at the times it intends to flight. a. supply b. demand c. equilibrium price d. break-even point
Answers: 2
You know the right answer?
Activity a has a duration of 3 days and begins on the morning of monday the 4th. the successor activ...
Questions
question
Mathematics, 19.07.2021 01:00
question
Mathematics, 19.07.2021 01:00
question
Mathematics, 19.07.2021 01:00
Questions on the website: 13722363