Project managers must often face the challenge of compressing the project schedule. all of the following actions can be taken to reduce the duration of the critical path except:
a. overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
b. reduce the project scope and /or quality.
c. use the float in critical path activities
d. partially overlap sequential activities by using time leads.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:00
Cynthia is a hospitality worker in the lodging industry who prefers to cater to small groups of people. she might want to open a
Answers: 3
question
Business, 22.06.2019 12:30
Amap from a trade development commission or chamber of commerce can be more useful than google maps for identifying
Answers: 1
question
Business, 22.06.2019 15:40
Acompany manufactures x units of product a and y units of product b, on two machines, i and ii. it has been determined that the company will realize a profit of $3 on each unit of product a and $4 on each unit of product b. to manufacture a unit of product a requires 7 min on machine i and 5 min on machine ii. to manufacture a unit of product b requires 8 min on mchine i and 5 min on machine ii. there are 175 min available on machine i and 125 min available on machine ii in each work shift. how many units of a product should be produced in each shift to maximize the company's profit p?
Answers: 2
question
Business, 22.06.2019 22:00
What resourse is both renewable and inexpensive? gold coal lumber mineral
Answers: 1
You know the right answer?
Project managers must often face the challenge of compressing the project schedule. all of the follo...
Questions
Questions on the website: 13722361