The for an activity is the latest possible time an activity might begin without delaying the project finish date.
a. late start date.
b. early finish date.
c. early start date
d. late finish date

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
During the first month of operations, martinson services, inc., completed the following transactions: jan 2 martinson services received $65,000 cash and issued common stock to the stockholders. 3 purchased supplies, $1,000, and equipment, $12,000, on account. 4 performed services for a customer and received cash, $5,500. 7 paid cash to acquire land, $39,000. 11 performed services for a customer and billed the customer, $4,100. martinson expects to collect within one month 16 paid for the equipment purchased january 3 on account. 17 paid for newspaper advertising, $600. 18 received partial payment from customer on account, $2,000. 22 paid the water and electricity bills, $430. 29 received $2,600 cash for servicing the heating unit of a customer. 31 paid employee salary, $2,900. 31 declared and paid dividends of $1,800. requirements 1. record each transaction in the journal. key each transaction by date. explanations are not required. 2. post the transactions to the t-accounts, using transaction dates as posting references. label the ending balance of each account bal, as shown in the chapter. 3. prepare the trial balance of martinson services, inc., at january 31 of the current year. 4. mark martinson, the manager, asks you how much in total resources the business has to work with, how much it owes, and whether january was profitable (and by how much)?
Answers: 1
question
Business, 22.06.2019 02:00
4. suppose that pollution in a neighborhood comes from two factories, with marginal benefit curves given by mb1 = 12 – p1 and mb2 = 8 – p2. the level of pollution in the neighborhood is given by p = p1 + p2. the government wants to limit pollution by instituting a pollution-rights market. the government’s desired level of p is 10, so it prints 10 pollution rights and offers them for sale to the firms.a)find the equilibrium selling price of a pollution right, as well as the allocation of rights (and hence pollution levels) across the two factories. b)repeat part (a) for the case where the government’s desired level of pollution equals 14. c)comment on the usefulness of a pollution rights market in achieving efficient levels of pollution abatement.
Answers: 2
question
Business, 22.06.2019 02:20
Each month, business today publishes a news piece about an innovative product, service, or business. such soft news is generally written by a freelance business writer and is known as a
Answers: 2
question
Business, 22.06.2019 02:30
Question 1 which of the following tasks use your roommate as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough spoon cookies onto the tray unload the cookies from the oven pack the cookies 1 points question 2 which of the following tasks use the tray(s) as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough bake the cookies cool the cookies accept payment 1 points question 3 determine the task time for the following tasks. fill integer numbers into the blank (e.g., 5 rather than 5.0) wash and mixing the dough: minute(s)/order spoon cookies onto the tray: minute(s)/order set up timer: minute(s)/order bake: minute(s)/order cool the cookies: minute(s)/order pack the cookies: minute(s)/order accept payment: minute(s)/order 2 points question 4 q4: determine the cycle time for the following resources. fill integer numbers into the blank (e.g., 5 rather than 5.0) kristen (you): minute(s) roommate: minute(s) oven: minute(s) 2 points question 5 what is the capacity rate (in orders/hour) of the roommate? 1 points question 6 what is the capacity rate (in orders/hour) of the whole process? 2 points question 7 how long (in minutes) it takes to process the first order?
Answers: 3
You know the right answer?
The for an activity is the latest possible time an activity might begin without delaying the projec...
Questions
question
Social Studies, 13.04.2021 14:50
question
Mathematics, 13.04.2021 14:50
question
Mathematics, 13.04.2021 14:50
question
Mathematics, 13.04.2021 14:50
question
English, 13.04.2021 14:50
Questions on the website: 13722367