Activity 7-8 is directly preceded by two activitiesactivity 5-7 and activity 6-7. activity 5-7 has an expected time of five and an es time of six. activity 6-7 has an expected time of seven and an es time of seven. activity 7-8 has an expected time of 10. the es for activity 7-8 is: a) 11b) 14c) 21d) 24e) 25

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 13:00
What is the percentage change in price for a zero coupon bond if the yield changes from 6.56.5% to 5.55.5%? the bond has a face value of $1 comma 0001,000 and it matures in 1010 years. use the price determined from the first yield, 6.56.5%, as the base in the percentage calculation?
Answers: 2
question
Business, 21.06.2019 20:30
technology is the application of knowledge and tools to solve problems and perform tasks more efficiently. t/f
Answers: 1
question
Business, 21.06.2019 23:30
You are frustrated to find that the only way to contact the customer service department is to make a phone call. the number listed would result in long distance charges to your phone bill. which issue should be addressed by the company to keep its crm in line with your expectations?
Answers: 2
question
Business, 22.06.2019 02:20
Each month, business today publishes a news piece about an innovative product, service, or business. such soft news is generally written by a freelance business writer and is known as a
Answers: 2
You know the right answer?
Activity 7-8 is directly preceded by two activitiesactivity 5-7 and activity 6-7. activity 5-7 has a...
Questions
question
Mathematics, 03.12.2021 01:00
question
Mathematics, 03.12.2021 01:00
question
Mathematics, 03.12.2021 01:00
Questions on the website: 13722367