Marko shioda, master scheduler at randall manufacturing company, prepared the following mps for one of the firm's major end products, the genuine whatcha macallit.
week # 1 2 3
mps 150 120 50
mariko is concerned about this schedule’s impact on widgets. it takes 3 widgets to make each whatchamacalit. the two bottleneck work centers for producing widgets are the "paint" work center and also the "final test" work center. the production manager has indicated that testing each widget requires 0.3 hours and painting each widget requires .5 hours. calculate the labor hours needed (rough-cut capacity analysis) for the "paint" work center. week # 1 2 3widget paint
![ansver](/tpl/images/cats/User.png)
Answers: 3
Another question on Business
![question](/tpl/images/cats/ekonomika.png)
Business, 21.06.2019 22:50
The winston company estimates that the factory overhead for the following year will be $1,250,000. the company has decided that the basis for applying factory overhead should be machine hours, which is estimated to be 50,000 hours. the total machine hours for the year were 54,300. the actual factory overhead for the year were $1,375,000. determine the over- or underapplied amount for the year.
Answers: 1
![question](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 11:50
Which of the following does not offer an opportunity for timely content? evergreen content news alerts content that suits seasonal consumption patterns content that matches a situational trigger content that addresses urgent pain points
Answers: 2
![question](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 15:00
Oerstman, inc. uses a standard costing system and develops its overhead rates from the current annual budget.the budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours.(practical capacity is 500,000 hours)annual budgeted overhead costs total $772,800, of which $556,800 is fixed overhead.a total of 119,300 units, using 478,000 direct labor hours, were produced during the year.actual variable overhead costs for the year were $260,400 and actual fixed overhead costs were $555,450.required: 1. compute the fixed overhead spending variance and indicate if favorable or unfavorable.2. compute the fixed overhead volume variance and indicate if favorable or unfavorable.
Answers: 3
![question](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 18:40
Under t, the point (0,2) gets mapped to (3,0). t-1 (x,y) →
Answers: 3
You know the right answer?
Marko shioda, master scheduler at randall manufacturing company, prepared the following mps for one...
Questions
![question](/tpl/images/cats/istoriya.png)
![question](/tpl/images/cats/biologiya.png)
![question](/tpl/images/cats/biologiya.png)
Biology, 08.10.2021 14:00
![question](/tpl/images/cats/istoriya.png)
![question](/tpl/images/cats/himiya.png)
![question](/tpl/images/cats/en.png)
![question](/tpl/images/cats/mat.png)
![question](/tpl/images/cats/fizika.png)
Physics, 08.10.2021 14:00
![question](/tpl/images/cats/mat.png)
![question](/tpl/images/cats/informatica.png)
Computers and Technology, 08.10.2021 14:00
![question](/tpl/images/cats/himiya.png)
Chemistry, 08.10.2021 14:00
![question](/tpl/images/cats/istoriya.png)
History, 08.10.2021 14:00
![question](/tpl/images/cats/mat.png)
Mathematics, 08.10.2021 14:00
![question](/tpl/images/cats/mat.png)
![question](/tpl/images/cats/istoriya.png)
![question](/tpl/images/cats/biologiya.png)
![question](/tpl/images/cats/himiya.png)
![question](/tpl/images/cats/istoriya.png)
History, 08.10.2021 14:00
![question](/tpl/images/cats/mat.png)
![question](/tpl/images/cats/en.png)
English, 08.10.2021 14:00