Abc construction has developed the following set of activities for its budgeting process.

activity

predecessor

normal activity time (days)

resulting activity time if activity is crashed (days)

total cost to complete activity in normal time

total cost to complete activity in crash time

a

--

4

2

$200

$600

b

a

6

3

$300

$1200

c

a

4

1

$300

$900

d

b, c

3

2

$500

$550

e

d

4

1

$500

$1700

a) using the normal times, what is the critical path and project completion time for the budgeting process? also, what is the cost to complete the project based on the normal times?

b) if we want to reduce the project completion time to the minimum possible time by crashing activities, what is the new project completion time and what is the new total project cost?

c) modify the problem as follows. there is now an indirect cost of $75 per day, which is in addition to the cost identified above. there is also a penalty cost of $200 per day for any project completion time over 11 days. what is the minimum cost schedule for the project and what is the total cost for this schedule? identify what are the time and the path of this minimum cost schedule.

d) suppose that the company wants to crash the project 4 days. based on the information provided in the table and in part c) and the results from part c), what would the minimum penalty cost have to be for this to be supported by the economics in the problem? assume that the indirect cost remains at $75 per day.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 13:10
You have recently been made a department head of the new regional office. in getting to know your departmental staff, you have noticed that one of your inexperienced employees is not following through on assigned tasks. she is enthused about her new job and wants to get ahead in the organization. which alternative represents the most effective leadership style: a. discuss the lack of follow-through with her and explore thealternative ways this problem can be solved. b. specify what she must do to complete the tasks but incorporate any suggestions she may have. c. define the steps necessary for her to complete the assigned tasks and monitor her performance frequently. d. let her know about the lack of follow-through and give hermore time to improve her performance.
Answers: 1
question
Business, 22.06.2019 16:40
Shawn received an e-mail offering a great deal on music, movie, and game downloads. he has never heard of the company, and the e-mail address and company name do not match. what should shawn do?
Answers: 2
question
Business, 22.06.2019 17:10
To : of $25 up to 35 2 35 up to 45 5 45 up to 55 7 55 up to 65 20 65 up to 75 16 is$25 up to $35 ?
Answers: 1
question
Business, 23.06.2019 04:40
2. a computer equipment was acquired at the beginning of the year at a cost of $56,000 with an estimated residual value of $5,000, and an estimated useful life of five years. determine the second year’s depreciation expense using the straight-line method.
Answers: 3
You know the right answer?
Abc construction has developed the following set of activities for its budgeting process.

Questions
Questions on the website: 13722360