subject
Business, 05.11.2019 02:31 angeljohnson2081

Aproject to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. a major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. the planners were expecting to be only54% through the third activity at this time. the first activity involves prepping the site for the bridge. it was expected that this would cost $1,440,000 and it was done for only $1,320,000. the second activity was the pouring of concrete for the bridge. this was expected to cost $10,520,000 but was actually done for $9,020,000. the third and final activity is the actual construction of the bridge superstructure. this was expected to cost a total of $8,520,000. to date, they have spent $5,020,000 on the superstructure. calculate the schedule variance?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
Abond is issued for less than its face value. which statement most likely would explain why? a. the bond's contract rate is higher than the market rate at the time of the issue. b. the bond's contract rate is the same as the market rate at the time of the issue. c. the bond's contract rate is lower than the market rate at the time of the issue. d. the bond isn't secured by specific assets of the corporation.
Answers: 1
question
Business, 21.06.2019 21:50
The next dividend payment by savitz, inc., will be $2.08 per share. the dividends are anticipated to maintain a growth rate of 6 percent forever. if the stock currently sells for $42 per share, what is the required return?
Answers: 2
question
Business, 22.06.2019 19:00
What is an equation of the line in slope intercept formm = 4 and the y-intercept is (0,5)y = 4x-5y = -5x +4y = 4x + 5y = 5x +4
Answers: 1
question
Business, 22.06.2019 20:10
The gilbert instrument corporation is considering replacing the wood steamer it currently uses to shape guitar sides. the steamer has 6 years of remaining life. if kept,the steamer will have depreciaiton expenses of $650 for five years and $325 for the sixthyear. its current book value is $3,575, and it can be sold on an internet auction site for$4,150 at this time. if the old steamer is not replaced, it can be sold for $800 at the endof its useful life. gilbert is considering purchasing the side steamer 3000, a higher-end steamer, whichcosts $12,000 and has an estimated useful life of 6 years with an estimated salvage value of$1,500. this steamer falls into the macrs 5-year class, so the applicable depreciationrates are 20.00%, 32.00%, 19.20%, 11.52%, 11.52%, and 5.76%. the new steamer is fasterand allows for an output expansion, so sales would rise by $2,000 per year; the newmachine's much greater efficiency would reduce operating expenses by $1,900 per year.to support the greater sales, the new machine would require that inventories increase by$2,900, but accounts payable would simultaneously increase by $700. gilbert's marginalfederal-plus-state tax rate is 40%, and its wacc is 15%.a. should it replace the old steamer? b. npv of replace = $2,083.51
Answers: 2
You know the right answer?
Aproject to build a new bridge seems to be going very well since the project is well ahead of schedu...
Questions
question
Mathematics, 16.06.2020 15:57
question
Mathematics, 16.06.2020 15:57
question
Mathematics, 16.06.2020 15:57
question
Mathematics, 16.06.2020 15:57
Questions on the website: 13722360