Given the following information about a small project, task duration immediateestimates predecessorsa 2 days noneb 5 days ac 4 days bd 9 days ae 4 days b & df 12 days e & cdraw a network diagram. identify the critical path, earliest start and finish and slack for each task. using ms excel, produce a gantt chart for this project. what would happen if a new estimate for task d increases its expected duration from 9 days to 11 days? would the project take longer? would anything else change?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:40
Maria am corporation uses the weighted-average method in its process costing system. the baking department is one of the processing departments in its strudel manufacturing facility. in june in the baking department, the cost of beginning work in process inventory was $4,880, the cost of ending work in process inventory was $1,150, and the cost added to production was $25,200. required: prepare a cost reconciliation report for the baking department for june.
Answers: 2
question
Business, 22.06.2019 03:00
Which of the following is not a consideration when determining your asset allocation
Answers: 3
question
Business, 22.06.2019 08:00
Shrieves casting company is considering adding a new line to its product mix, and the capital budgeting analysis is being conducted by sidney johnson, a recently graduated mba. the production line would be set up in unused space in the main plant. the machinery’s invoice price would be approximately $200,000, another $10,000 in shipping charges would be required, and it would cost an additional $30,000 to install the equipment. the machinery has an economic life of 4 years, and shrieves has obtained a special tax ruling that places the equipment in the macrs 3-year class. the machinery is expected to have a salvage value of $25,000 after 4 years of use. the new line would generate incremental sales of 1,250 units per year for 4 years at an incremental cost of $100 per unit in the first year, excluding depreciation. each unit can be sold for $200 in the first year. the sales price and cost are both expected to increase by 3% per year due to inflation. further, to handle the new line, the firm’s net working capital would have to increase by an amount equal to 12% of sales revenues. the firm’s tax rate is 40%, and its overall weighted average cost of capital, which is the risk-adjusted cost of capital for an average project (r), is 10%. define “incremental cash flow.” (1) should you subtract interest expense or dividends when calculating project cash flow?
Answers: 1
question
Business, 22.06.2019 13:50
The retained earnings account has a credit balance of $24,650 before closing entries are made. if total revenues for the period are $77,700, total expenses are $56,900, and dividends are $13,050, what is the ending balance in the retained earnings account after all closing entries are made?
Answers: 2
You know the right answer?
Given the following information about a small project, task duration immediateestimates predecessors...
Questions
question
Social Studies, 18.07.2019 00:00
Questions on the website: 13722362