Aproduction line is to be designed for a job with four tasks. the task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. after line balancing, the largest possible assigned cycle time is minutes, and the smallest possible assigned cycle time is minutes.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:00
True or false: a smart store layout moves customers in and out as fast as possible. a) true b) false
Answers: 2
question
Business, 22.06.2019 04:40
How long have u been on dis website
Answers: 2
question
Business, 22.06.2019 08:00
Why is it vital to maintain a designer worksheet? a. it separates the designs chosen for the season from those rejected by the company. b. it keeps a record of all designs created by the designer for a season. c. it charts out the development of an entire line through the season and beyond. d. it tracks the development of a design along with costing and production details. done
Answers: 1
question
Business, 22.06.2019 18:00
Large public water and sewer companies often become monopolies because they benefit from although the company faces high start-up costs, the firm experiences average production costs as it expands and adds more customers. smaller competitors would experience average costs and would be less
Answers: 1
You know the right answer?
Aproduction line is to be designed for a job with four tasks. the task times are 2.4 minutes, 1.4 mi...
Questions
question
Mathematics, 17.11.2019 23:31
question
English, 17.11.2019 23:31
question
Advanced Placement (AP), 17.11.2019 23:31
Questions on the website: 13722367