Business, 27.06.2019 00:40 trvptrav

You have determined that an ocf of $142,098 will result in a zero net present value for a project, which is the minimum requirement for project acceptance. the fixed costs are $418,000 and the contribution margin per unit is $87.20. the company feels that it can realistically capture 4.5 percent of the 120,000 unit market for this product. the tax rate is 34 percent and the required rate of return is 11 percent. should the company develop the new product? why or why not? yes. the project's required rate of return exceeds the expected irr. yes. the expected level of sales exceeds the required level of production. no. the required level of production exceeds the expected level of sales. no; the contribution margin is too high no. the ocf is too low.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 03:30
When the federal reserve buys and sells bonds to member banks, it is called a. monetary policy b. reserve ratio c. interest rate adjustment d. open market operations
Answers: 2
question
Business, 22.06.2019 06:00
Select the correct answer a research organization conducts certain chemical tests on samples. they have data available on the standard results. some of the samples give results outside the boundary of the standard results. which data mining method follows a similar approach? o a. data cleansing ob. network intrusion o c. fraud detection od. customer classification o e. deviation detection
Answers: 1
question
Business, 22.06.2019 08:00
How do communism and socialism differ in terms of the role that government plays in the economy ?
Answers: 1
question
Business, 22.06.2019 12:50
You are working on a bid to build two city parks a year for the next three years. this project requires the purchase of $249,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the three-year project life. ignore bonus depreciation. the equipment can be sold at the end of the project for $115,000. you will also need $18.000 in net working capital for the duration of the project. the fixed costs will be $37000 a year and the variable costs will be $148,000 per park. your required rate of return is 14 percent and your tax rate is 21 percent. what is the minimal amount you should bid per park? (round your answer to the nearest $100) (a) $214,300 (b) $214,100 (c) $212,500 (d) $208,200 (e) $208,400
Answers: 3
You know the right answer?
You have determined that an ocf of $142,098 will result in a zero net present value for a project, w...