The purpose of determining the critical path on a pert network is to: identify the sequence of tasks that takes the longest to complete. estimate a payment schedule so that a budget can be established. find the sequence of events that is the most expensive to complete. establish a delivery schedule for a just-in-time inventory control program.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 06:40
After the 2008 recession, the amount of reserves in the us banking system increased. because of federal reserve actions, required reserves increased from $44 billion to $60 billion. however, banks started holding more reserves than required. by january 2009, banks were holding $900 billion in excess reserves. the federal reserve started paying interest on the excess reserves that the banks held. what possible impact will these unused reserves have on the economy?
Answers: 1
question
Business, 22.06.2019 11:10
Wilson company paid $5,000 for a 4-month insurance premium in advance on november 1, with coverage beginning on that date. the balance in the prepaid insurance account before adjustment at the end of the year is $5,000, and no adjustments had been made previously. the adjusting entry required on december 31 is: (a) debit cash. $5,000: credit prepaid insurance. $5,000. (b) debit prepaid insurance. $2,500: credit insurance expense. $2500. (c) debit prepaid insurance. $1250: credit insurance expense. $1250. (d) debit insurance expense. $1250: credit prepaid insurance. $1250. (e) debit insurance expense. $2500: credit prepaid insurance. $2500.
Answers: 1
question
Business, 22.06.2019 17:30
After the embarrassing sign incident at the restaurant you own, you decide to offer employees a six-week fundamental writing skills workshop. a local business communication instructor, who has experience teaching writing skills at treleaven community college, will facilitate the sessions. to encourage employees to attend these optional sessions, write an email that explains why you’re offering the workshop and why employees should participate.
Answers: 2
question
Business, 22.06.2019 17:30
Dr. sperry, a biologist, is using excel to track growth rates of different populations of bacteria. she has a very complex formula in one cell. it begins with “round”. dr. sperry would like to see exactly how excel’s calculation reached the final rounded value that she sees in the cell. what could dr. sperry do to best understand how the calculation was made? try different formulas on her own until she reaches the value shown in excel click on the evaluate formula button in the formulas tab and then click “step in” select the cell and then look at the formula in the formula field of the ribbon remove “round” from the formula in order to see the actual value before rounding
Answers: 2
You know the right answer?
The purpose of determining the critical path on a pert network is to: identify the sequence of task...
Questions
question
Biology, 27.10.2020 20:00
question
Mathematics, 27.10.2020 20:00
question
Mathematics, 27.10.2020 20:10
question
Mathematics, 27.10.2020 20:10
question
English, 27.10.2020 20:10
Questions on the website: 13722359